Tuesday, June 28, 2011

assisnment 5 time programming

Week 5
21/03/2011 - 23/03/2011

For this week we were reading the plans of the sleepout, and we started setting out the floor joists for the sleepout doing the bearers, joists and also insulating the floor.

Week 6
28/03/2011 - 30/03/2011 
For this week we were continuing with setting out the floor joists, putting the temporary floor and we were reading/discussing the plan

Week 7
04/04/2011 - 06/04/2011
For this week we were starting the wall framing the top plate and bottom plate for the back, front and the side wall.

Week 8
11/04/2011 - 13/04/2011
For this week we were continunig with building the walls doing the studs,nogs.

Week 9
02/05/2011 - 04/04/2011
For this week we started doing the bbq tables, and we started doing the roof of the house, the roof rafters, purlins, fly rafters and putting the self supporting paper on top.

Week 10
09/05/2011 - 11/05/2011
for this we week were doing the wing walls for the sleepout and we were doing the fascia board and the installind the iron trapezoidal on the roof.

Week 11
16/05/11 - 18/05/2011
For this we week were wrapping the building, and we stared doing the soffis and the rhondo